Jineng Holding Tashan No. 2 Power Plant Project
Project overview
Project Location
Jineng Holding Tashan No. 2 Power Plant Project
Project Time
Project introduction
Scale: 2×660MW
Voltage Level: 550kV
Owner Profile:
The Tongmei Tashan Power Plant Phase II Expansion Project is the first project in Shanxi Province to obtain environmental impact assessment and approval for low-calorific coal-fired power generation. The project started its preliminary work in 2007 and obtained approval in December 2013. The project is estimated to have a total investment of 5.022 billion yuan and will construct two 660,000 kW ultra-supercritical direct air-cooled low-calorific coal-fired generating units. It is planned to achieve dual-unit operation this October.
"The project officially started on March 1, 2016, with a planned construction period of 21 months, 8 months less than the standard construction period for the power industry and 3 months less than the approved implementation plan for low-calorific coal-fired power generation projects in Shanxi Province." A person in charge of Tongmei Datang Tashan Second Power Generation Co., Ltd. introduced to the reporter. To ensure the project's timely completion and operation, the company strictly followed the schedule from the outset, formulating a detailed construction plan and clearly defining the construction progress, quality requirements, and safety guarantees for each stage. Following the construction plan, the construction workers braved the cold and heat, overcoming various unfavorable factors to push forward the project construction with all their might.
Keywords:
Smart grid
Related projects